Reminder: Buffalo Bayou Watershed Flood Bond Meeting July 30

Also Barker Reservoir Meeting on Aug. 1

 

July 23, 2018

The Harris County Flood Control District and members of county commissioners’ court continue to hold meetings around the county to present proposals for projects attempting to reduce the hazard of flooding.

The meeting about projects proposed in the Buffalo Bayou watershed will be held on Monday, July 30, from 6 to 8 p.m. at the Memorial Drive United Methodist Church, 12955 Memorial Drive in Houston. A meeting to present projects proposed for the Barker Reservoir watershed is scheduled for Wednesday, Aug. 1, from 6 to 8 p.m. at Memorial Parkway Junior High, 21203 Highland Knolls Drive in Katy. Buffalo Bayou flows from its headwaters near Katy into and through Barker Dam.

The projects are to be funded with the proceeds of a $2.5 billion bond issue should the voters approve on August 25. The bonds would be issued over a period of ten to fifteen years, according to the flood control district, and repaid through a property tax increase of no more than two-three cents per $100 of home valuation. Homeowners with an over-65 or disabled exemption and a home worth $200,000 or less would not pay any additional taxes, according to the district.

Most of the projects proposed are projects that had long been planned. For instance, a controversial project to remove forest and excavate basins to capture and temporarily hold overflow on the south bank of Buffalo Bayou in Terry Hershey Park is listed with a $10 million cost estimate. The project in its initial stages would allegedly create 60-100 acre-feet of temporary storage alongside the bayou. The linear detention, siphoning flow out of the bayou, is planned to compensate for eventual additional City of Houston drainage into the bayou from neighborhood streets.

Barker and Addicks dams both drain into Buffalo Bayou, and overflow from Cypress Creek on the rapidly developing Katy Prairie in northwest Harris County also drains into the overburdened Addicks Reservoir, adding to the pressure of runoff into Addicks and the bayou.

Other than the Hershey Park detention project, some $21 million is slated for a new detention basin north of John Paul’s Landing on Upper Langham Creek, which drains into Addicks.

However, most of the projects listed for these watersheds mainly focus on repairing channels and improving conveyance – making more stormwater flow faster into and through the reservoirs. This has the potential to cause more problems and more flooding. Modern practice elsewhere is to focus on slowing the flow, making room for the river with wider floodplains. We would hope for more money to be spent on land aquisition, buyouts in floodplains, preservation of undeveloped land, forest, wetlands, prairies, and riparian vegetaton; creation of green space, restoring meanders, and programs to encourage slowing of rain runoff beginning with individuals and neighborhoods.

There are also funds proposed to be used in collaboration with Army Corps of Engineers, which owns and operates Addicks and Barker, to evaluate the effectiveness and operation of those 70-year-old dams.

A complete list of projects can be found on the flood control district’s website. The website also offers a way to make comments about the projects.

The meetings are not set up for the public to engage officials or voice opinions. They are informative only – with numerous stations staffed by flood control personnel to explain projects. However, paper and pencils are provided for citizens to write comments.

A house damaged by Harvey floodwaters in a still-recovering neighborhood north of Buffalo Bayou in west Houston. Photo on June 12, 2018, by SC

Wasting Money the Old-Fashioned Way

Costly Bayou Repairs Do More Harm Than Good, Won’t Last

Nov. 21, 2016

Updated April 23, 2017 — The Harris County Flood Control District reports that repair costs through March 2017 are $1.25 million. Terry Hershey Park remains closed until construction work is complete.

See also “Commissioner Radack Responds.”

From a distance you could hear the monstrous roar of the heavy equipment in the woods. Following deep, wide tracks smashed into the bare dirt along the bank of Buffalo Bayou, passing large cottonwoods apparently cut to make way for the big equipment, we came across a scene of troubling destruction.

A gigantic articulated 30-ton dump truck with six massive wheels was slowly rolling towards us with a large load of fresh dirt and dripping mud dug up from the bayou bank. Further along a 60-ton excavator on tracks sat on the very edge of the bank, expertly swiveling back and forth, scraping up the dirt bank and dumping it into the truck, scooping up loads of white limestone rock and dropping it in a layer where the excavated bank once was.

We’d seen the eroded bank before the “repairs” began. This damage was far worse.

It didn’t have to be this way.

Read the rest of this story.

Dump truck and excavator at work on the north bank of Buffalo Bayou in Terry Hershey Park on Nov. 3, 2016. Photo by Jim Olive

Dump truck and excavator at work on the north bank of Buffalo Bayou in Terry Hershey Park on Nov. 3, 2016. Photo by Jim Olive

 

Enjoy Your Flood!

County Commissioner Provokes Wrath of Flood Victims

Aug. 8, 2016

Updated Aug. 9. Radack Doubles Down, Stands His Ground. Read Here.

Harris County Precinct 3 Commissioner Steve Radack has unleashed a flood of outrage by telling an audience of several hundred citizens in an area of the city heavily damaged by flooding that “some people enjoy flooding.”

Harris County Commissioner Steve Radack telling flood victims that some people enjoy floods because they get new cars and remodeled homes. Image courtesy of Cynthia Neely, Aug. 4, 2016.

Harris County Commissioner Steve Radack telling flood victims that some people enjoy floods because they get new cars and remodeled homes. Image courtesy of Cynthia Neely, Aug. 4, 2016.

The large audience at a meeting of the Cypress Coalition Thursday, Aug. 4, gasped and groaned when Radack took the podium, waved his hands, and said that “some people frankly over the years, in the years I’ve been doing this, that frankly enjoy floods about every seven years, because they want new cars, they want their homes redone.”

Only Rain Causes Flooding!

Cynthia Neely, board member of Residents Against Flooding (RAF), was at the meeting at the Metropolitan Baptist Church with RAF Chair Ed Browne. She reports that both Radack, who’s been in office for 27 years, and Mike Talbott, retiring director of the Harris County Flood Control District, blamed Mother Nature for flooding.

Read the rest of this post.

Empty at Last. Almost.

Buffalo Bayou Reservoirs Finally Drain Last of Flood Waters

July 6, 2016

The last of the storm water from the April 18 Tax Day floods has passed finally  through the gates of Addicks and Barker dams in western Harris County. (Almost, not quite. See comment below.) The reservoirs behind those 1940s-era earthen dams on Buffalo Bayou are normally empty in order to be ready to impound rainfall and runoff that would flood central Houston downstream.

The Army Corps of Engineers, which owns and operates the dams, was forced to release water through the dams at a high rate of flow – between 2,000 and 3,000 cubic feet per second (cfs) and more — for nearly three months in order to empty the record-high reservoirs, as frequent rains kept adding to the water level.

Base flow in Buffalo Bayou, as measured by the USGS gauge at Piney Point, is between 100 and 200 cfs. As of today the flow was still high – over 1,000 cfs.

The dams on Buffalo Bayou are classified “extremely high risk,” in large part due to the damage that would occur to the nation’s fourth most populous city if the dams were to fail. A $72 million construction project to repair seepage problems and build new conduits has been delayed due to the high water level in the reservoirs.

You can listen to what Richard Long, who manages the dams for the Corps, had to say about the situation this morning to Dave Fehling of Houston Public Matters. Long is the supervisory natural resources manager for the Corps’ Galveston District and has been working at the dams for 35 years.

And look for a report from us soon about the impact of the high waters on Buffalo Bayou. Richard Hyde, a geologist who lives in neighboring Bear Creek Village, reports that the herds of deer that roam the 25,000 acres of federally-owned wooded parkland in the reservoirs seem greatly reduced. And sadly, Buffy the Bison, rescued in April from the flooded small zoo in Bear Creek Park, died shortly thereafter.

Barker Dam and Reservoir around midday on Sunday, June 5, 2016, as the dam gates were releasing impounded stormwater into Buffalo Bayou. The 12,000-acre reservoir is located just west of Highway 6.

Barker Dam and Reservoir around midday on Sunday, June 5, 2016, as the dam gates were releasing impounded stormwater into Buffalo Bayou. The 12,000-acre reservoir is located just west of Highway 6.

From The Sky Above: Barker Dam and Reservoir

June 7, 2016

Houston photographer Jim Olive took this photo of Barker Dam and Reservoir in west Houston on Sunday, June 5, at around 11:30 a.m.

The dam gates had just been opened, and water from recent rains was pouring from the reservoir’s temporary lake into Buffalo Bayou, which flows through Barker Reservoir through the center of Houston and into Galveston Bay. Water impounded from several creeks behind nearby Addicks Dam also flows into Buffalo Bayou below Barker Dam. The dams were built in the 1940s to protect downtown Houston from catastrophic flooding.

Barker Dam and Reservoir around midday on Sunday, June 5, 2016, as the dam gates were releasing impounded stormwater into Buffalo Bayou. The 12,000-acre reservoir is located just west of Highway 6.

Barker Dam and Reservoir around midday on Sunday, June 5, 2016, as the dam gates were releasing impounded stormwater into Buffalo Bayou. The 12,000-acre reservoir is located just west of Highway 6. Photo by Jim Olive.

Record rains that fell on west Houston and elsewhere on April 18 filled the two flood control reservoirs with unprecedented amounts of water. Rains since then have slowed releases from the normally empty basins, which contain large, forested parks and recreational facilities. The Army Corps of Engineers, which owns and operates the dams, closes the dam gates during a rain, and rain adds more water to the reservoirs, which must be emptied as quickly as possible in order to create room to hold back future stormwater. Maximum capacity, the volume beyond which water will begin to spill around the ends of the dams, is 199,643 acre-feet for Addicks and 209,600 acre-feet for Barker. Addicks Reservoir is just to the north of Barker on the northern side of Interstate 10.

The combined peak pool behind the two reservoirs was more than 206,000 acre-feet around April 22, with Addicks reaching some 122,000 acre-feet or a little more than two-thirds of maximum capacity. Despite record high extended releases from the dams for the last seven weeks, the two reservoirs have been drained by less than half, standing at a combined volume of 114,210 acre-feet on Tuesday early afternoon.

Dammed If They Do, Dammed If They Don’t

The Conundrum of the Buffalo Bayou Dams

Why so much water for so long in Buffalo Bayou?

May 26, 2016

The water in the normally empty reservoir had dropped only a few feet by the time we stood on the earthen dam looking down at the dark, opaque blue-gray surface. After almost a month, the rippling water below was still some twenty-three feet deep, and extended as far as we could see along the thirteen-mile long dam and far into the thousands of acres of flooded woods.

It had taken only a little more than twenty-four hours for the rains that began on April 18 to fill the vast flood control reservoirs in west Houston with a record amount of water: a total of more than 206,000 acre feet, a massive amount of water. Imagine 206,000 acres covered in a foot of water. Enough to cover more than eight times the acreage of both reservoirs to a depth of one foot. That much water would take an estimated four weeks to drain, according to reports at the time.

But that was only if there was no more rain. There was more rain, and it was taking much longer. The reservoirs, vast wooded parks with recreational facilities and nature paths, are still draining. As of May 24, the combined total of the two reservoirs was still about 90,000 acre-feet, down to a little less than half.

And Buffalo Bayou was still flowing high and fast, higher and faster for longer than ever before. Property owners upstream had flooded and property owners downstream who had hoped for more moderate flows were instead seeing long-standing trees falling into the fast-flowing stream, banks eroding, sediment collecting, debris causing water to back up onto their property.

Why was this happening and is there a way out of it?

Read the rest of this post.

The platform containing the control panel for the gates at Barker Dam. Photo taken May 17, 2016

The platform containing the control panel for the gates at Barker Dam standing in what would normally be an empty reservoir and park. Photo taken May 17, 2016

Out on the Bayou with the Boy Scouts

Documenting Wildlife Tracks and Weird Nature Stuff

April 6, 2016

We went out with Paul Hung and his band of intrepid Boy Scouts last week to document wildlife tracks on the banks of Buffalo Bayou.

We saw a lot of interesting things, including footprints of mysterious creatures behaving in puzzling ways, some strange yellow liquid, and flying seat cushions nesting in the trees.

This was the second outing for Paul and his teen-aged colleagues from Boy Scout Troop 55, Sam Houston Area Council. For his Eagle Scout Service Project, Paul proposed documenting the wildlife on the bayou as it flows along the southern edge of Memorial Park. Save Buffalo Bayou is the beneficiary, and we hope to publish Paul’s results as a pamphlet.

Fortunately the flow was very low, less than 200 cubic feet per second, which is about base flow in the bayou when it hasn’t been raining. The Army Corps of Engineers assured us in advance that the reservoirs in the dams upstream were empty, and barring any unforeseen weather event, the water would be low enough for us to see plenty of activity on the mud and sand of the banks. Which we did.

Paul was well organized. He handed out clipboards, small rulers, and post-it notes, and instructed his fellow scouts to use these with the GPS app on their cell phones to take photos and number and record the size of tracks. The group was divided into pairs in canoes. A few adults went along too, including Richard Hung, father of Paul, and Troop 55 Assistant Scoutmaster Janice Van Dyke Walden.

 

From left to right: Janice Walden, Richard Hung, and Troop 55 Boy Scouts Paul Hung, Andrew Hung, Nicolas Dinius, Chance Coleman, Jackson Douglas, Kendall Barnes, and Joseph Hlavinka at the Woodway Boat Launch in Memorial Park. Photo by Jim Olive on April 2, 2016

From left to right: Janice Walden, Richard Hung, and Troop 55 Boy Scouts Paul Hung, Andrew Hung, Nicolas Dinius, Chance Coleman, Jackson Douglas, Kendall Barnes, and Joseph Hlavinka at the Woodway Boat Launch in Memorial Park. Photo by Jim Olive on April 2, 2016

Tracks Everywhere

There were tracks everywhere. Creatures crawling, slithering, hopping and tiptoeing across the sand, burrowing, strolling, turning about and flying away; digging holes, chasing each other, stepping and sliding in and out of the water.

Read the rest of this story.

No Changes in Operation of Buffalo Bayou Dams

Release Rates May Be Looked At in Future

March 13, 2016

It was a dark and stormy night. Thunder boomed and heavy rain pelted the roof as a small group of us sat nervously in the middle of the rising Addicks Reservoir in far west Houston listening to the district commander of the Army Corps of Engineers tell us Addicks and Barker dams are safe.

Flanking Col. Richard Pannell last Wednesday, March 9, was a panel of officials from the Corps’ Galveston District office, as well as representatives from the Harris County Flood Control District and Granite Construction, the company awarded the $71.9 million contract to replace the leaky conduits in the 70-year-old earthen dams. The audience was a small crowd of about thirty hardy citizens who had braved the heavy traffic and heavy rain and managed to find the Bear Creek Community Center in the middle of a dark, wet forest despite the wrong address in the Corps’ public notice.

Col. Pannell made a thorough and convincing presentation of the history of the dams, the current problems, and what is being done about them. Among other work, the conduits in the two dams will be entirely replaced by new conduits in separate locations. This process will take about three years. He emphasized that the dams were in no immediate danger of failing and explained that the dams are labeled “extremely high risk” because of the potential consequences to Houston, the nation’s fourth most populous city, in the unlikely event that the dams failed.

Dams Operating Normally Despite Leaks

There were several questions about the capacity of the dams and the impact of repairs on the rate of future releases of water impounded behind the dams. The pattern of extended high releases and rapid drops has been criticized for damaging property on the bayou and killing trees and vegetation that control erosion.

After the enormous Memorial Day storm last year, the Corps began releasing impounded stormwater at 3000 cubic feet per second (cfs) for the first time. Normally the release rate is limited to 2000 cfs as measured by the Piney Point gauge. The Corps does not release water from the dams during a rain event, and the high releases began on June 1 and continued for ten days, finally dropping on June 12. The banks were already saturated from the storm, and the damage from the extended high flow was plainly visible up and down the bayou.

Read the rest of this story.

Tree on private property downed by extended high water releases from Buffalo Bayou dams in June 2015. Photo courtesy of Don Jones.

Tree on private property downed by extended high water releases from Buffalo Bayou dams in June 2015. Photo courtesy of Don Jones.

 

Public Meeting on Buffalo Bayou Dams

Corps of Engineers to Issue Repair Update Wednesday, March 9

March 7, 2016

Updated March 14, 2016

The US Army Corps of Engineers, Galveston District, is holding a public meeting Wednesday, March 9, 2016, to update the public about progress in repairing the Addicks and Barker dams on South Mayde Creek and Buffalo Bayou in rapidly developing west Houston.

The two earthen dams, completed in the 1940s, were labeled “extremely high risk” in 2009 when engineers noticed seepage around the dams’ gates and ends following a heavy storm. The “extremely high risk” designation did not mean the dams were in danger of failing soon. But the possibility of failure combined with the dams’ location upstream of a major metropolitan area lifted the dams into the urgent category.

As a result, the reservoirs, which are dry reservoirs and contain one of the region’s largest parks and recreation areas, cannot be filled to capacity during storms, which impacts the way water is released from the dams before and after storms: faster and more often. (Correction: The Corps of Engineers says that the structural problems with the dams have had no impact on the capacity limit or release rates. This unnatural flow regime in turn impacts Buffalo Bayou downstream. (South Mayde Creek joins Buffalo Bayou just below the dams.) However, most of the flooding in Buffalo Bayou during heavy storms is caused by surface runoff from buildings, highways, streets, parking lots, and other paved surfaces below the dams, which are closed during rain events.

Read the rest of this post.

Barker Reservoir. Undated photo courtesy of USACE, Galveston District.

Barker Reservoir. Undated photo courtesy of USACE, Galveston District.