Wasting Money the Old-Fashioned Way

Costly Bayou Repairs Do More Harm Than Good, Won’t Last

Nov. 21, 2016

Updated April 23, 2017 — The Harris County Flood Control District reports that repair costs through March 2017 are $1.25 million. Terry Hershey Park remains closed until construction work is complete.

See also “Commissioner Radack Responds.”

From a distance you could hear the monstrous roar of the heavy equipment in the woods. Following deep, wide tracks smashed into the bare dirt along the bank of Buffalo Bayou, passing large cottonwoods apparently cut to make way for the big equipment, we came across a scene of troubling destruction.

A gigantic articulated 30-ton dump truck with six massive wheels was slowly rolling towards us with a large load of fresh dirt and dripping mud dug up from the bayou bank. Further along a 60-ton excavator on tracks sat on the very edge of the bank, expertly swiveling back and forth, scraping up the dirt bank and dumping it into the truck, scooping up loads of white limestone rock and dropping it in a layer where the excavated bank once was.

We’d seen the eroded bank before the “repairs” began. This damage was far worse.

It didn’t have to be this way.

Read the rest of this story.

Dump truck and excavator at work on the north bank of Buffalo Bayou in Terry Hershey Park on Nov. 3, 2016. Photo by Jim Olive

Dump truck and excavator at work on the north bank of Buffalo Bayou in Terry Hershey Park on Nov. 3, 2016. Photo by Jim Olive

 

State of the Bayou

Downed Trees. New Channel. New Riprap. Washed Out Sidewalks, Beavers, and Turtles

But Some Banks Naturally Rebuilding

Does It Make Sense to Repair?

Sept. 1, 2016

Updated Sept. 11, 2016

You could not step twice into the same river. Heraclitus

We finally had a chance recently to float down beautiful Buffalo Bayou to see how things have changed. Our trip took us past Memorial Park in the middle of Houston. We also biked along the bayou through Terry Hershey Park far upstream in west Houston below the dams to see what was happening there.

The good news is that some of the high banks that had slumped in Memorial Park and the Hogg Bird Sanctuary during the Memorial Day 2015 flooding are naturally rebuilding.

The bad news is that the River Oaks Country Club has added more riprap to the south bank, hard armoring the bank with ugly, damaging concrete rubble, including where it should not be.

Nature’s Miraculous Way of Restoring. For Free.

Houston has had multiple record-breaking rains and flooding since the spring of 2015. When Buffalo Bayou overflows its high banks, as it did in the Memorial Day flood of 2015, the banks in places sometimes slump or slide away. This happens when the overflowing water seeps through the ground and saturates layers of sandy clay that liquefy, sometimes causing the bank to give way. Buffalo Bayou is 18,000 years old, and this has been happening for a very long time.

This natural tendency to slump is one reason why we think attempting to engineer these banks as proposed by the $6 million Memorial Park Demonstration Project won’t work. It’s also the reason why we think building and repeatedly repairing sidewalks at the bayou’s edge is wasteful and foolish.

Read the rest of this story.

The same high bank three months later on August 4, 2016.

The south-facing high bank of the Hogg Bird Sanctuary collapsed during the Memorial Day flood in 2015. Now self-restored. Photo on August 4, 2016.

Out on the Bayou with the Boy Scouts

Documenting Wildlife Tracks and Weird Nature Stuff

April 6, 2016

We went out with Paul Hung and his band of intrepid Boy Scouts last week to document wildlife tracks on the banks of Buffalo Bayou.

We saw a lot of interesting things, including footprints of mysterious creatures behaving in puzzling ways, some strange yellow liquid, and flying seat cushions nesting in the trees.

This was the second outing for Paul and his teen-aged colleagues from Boy Scout Troop 55, Sam Houston Area Council. For his Eagle Scout Service Project, Paul proposed documenting the wildlife on the bayou as it flows along the southern edge of Memorial Park. Save Buffalo Bayou is the beneficiary, and we hope to publish Paul’s results as a pamphlet.

Fortunately the flow was very low, less than 200 cubic feet per second, which is about base flow in the bayou when it hasn’t been raining. The Army Corps of Engineers assured us in advance that the reservoirs in the dams upstream were empty, and barring any unforeseen weather event, the water would be low enough for us to see plenty of activity on the mud and sand of the banks. Which we did.

Paul was well organized. He handed out clipboards, small rulers, and post-it notes, and instructed his fellow scouts to use these with the GPS app on their cell phones to take photos and number and record the size of tracks. The group was divided into pairs in canoes. A few adults went along too, including Richard Hung, father of Paul, and Troop 55 Assistant Scoutmaster Janice Van Dyke Walden.

 

From left to right: Janice Walden, Richard Hung, and Troop 55 Boy Scouts Paul Hung, Andrew Hung, Nicolas Dinius, Chance Coleman, Jackson Douglas, Kendall Barnes, and Joseph Hlavinka at the Woodway Boat Launch in Memorial Park. Photo by Jim Olive on April 2, 2016

From left to right: Janice Walden, Richard Hung, and Troop 55 Boy Scouts Paul Hung, Andrew Hung, Nicolas Dinius, Chance Coleman, Jackson Douglas, Kendall Barnes, and Joseph Hlavinka at the Woodway Boat Launch in Memorial Park. Photo by Jim Olive on April 2, 2016

Tracks Everywhere

There were tracks everywhere. Creatures crawling, slithering, hopping and tiptoeing across the sand, burrowing, strolling, turning about and flying away; digging holes, chasing each other, stepping and sliding in and out of the water.

Read the rest of this story.

How Old Is Buffalo Bayou? Where Does It Come From?

Geology Lessons on the Bayou

March 27, 2016

Want to learn about the geology and natural history of Buffalo Bayou?

Save Buffalo Bayou is partnering with professional geologist Tom Helm, who also happens to be an outstanding naturalist and river guide, to offer floating classes on the geology of our 18,000-year-old mother bayou.

Paddle with Tom on a two-hour canoe trip down Buffalo Bayou and see some of our Pleistocene natural history right here in the middle of Houston. Learn all about the formation of the bluffs and sandstone rocks during the last ice age. See examples of depositional environments and fluvial processes. Find out why the banks are sandy and how sand moves downstream, why the river looks the way it does, and much more.

Geologist Tom Helm explaining 500,000-year-old sandstone on Buffalo Bayou.

Geologist Tom Helm explaining 500,000-year-old sandstone on Buffalo Bayou. Photo taken March 18, 2016

Where, When, Cost

The classes start at the Woodway boat launch in Memorial Park and float past the park and the Hogg Bird Sanctuary, through the historic natural area targeted for destruction by the Harris County Flood Control District. Multiple stops will be made along the way to examine features of interest.

The schedule depends on class size. One to four persons can be scheduled any day of the week, usually with no more than 48 hours’ notice. Groups larger than four persons (up to 30 persons maximum) are accepted only on weekends. These larger weekend groups need to schedule at least one month in advance.

Cost is $50 per person, which includes canoe and equipment, and light refreshments at the end. Discounts are available for academic faculty and students.

Note that the classes will be not take place if the flow of Buffalo Bayou is greater than 300 cubic feet per second (as measured by the Piney Point USGS gauge). At water levels above this, the sandstones are mostly obscured. If a trip is cancelled due to high water, students have the option of rescheduling or receiving a full refund.

For more information, contact Tom Helm.

Some Things We Learned Already: Why Mud Stinks

We floated with Tom recently for a preview of the geology class. Among the things we learned is why some of the mud stinks. The mud and the sand are filled with layers of organic matter, leaves mostly, and as the organic matter decomposes, it smells like … decomposing stuff. But it also builds soil for future vegetation. This process produces the mysterious oily sheen that you see floating on top of the mud sometimes.

We also learned to tell mud from sand from silt. (Hint: it’s a matter of the size of the grains.) Tom showed us how geologists rub the mud between their thumb and fingers to feel the size of the grains.

We studied the patterns in the sand, watched the grains of sand moving in the water, and learned about eddies and sediment deposition and transport. We saw a lot of animal tracks.

We learned to put the constantly changing bayou in the context of its natural process.

In every outthrust headland, in every curving beach, in every grain of sand there is the story of the earth.
Rachel Carson

Once-a-Boat-Launch at Woodway to Re-Open by Mid-December

Meanwhile Buffalo Bayou Busy Replanting, Beautifying

Sept. 5, 2015

A contractor has been found at last to take down the heavy-duty chain-link construction fencing, put up some railing, spread some gravel and sod, and restore the informational sign in that western part of Memorial Park that was once a popular boat launch and is now referred to by public officials as a drainage outfall.

Native, edible amaranth in the foreground growing on the bank of the Woodway drainage outfall. Smartweeds, snoutbean, and other plants, mostly native but also some invasive, in the background. Photo Aug. 28, 2015

Native, edible amaranth in the foreground planted by Buffalo Bayou on the bank of the Woodway drainage outfall. Smartweeds, snoutbean, and other plants, mostly native but also some invasive, in the background. Native plants like amaranth and smartweed stabilize the soil and help prepare for new forest growth. Non-native Bermuda and St. Augustine grasses planted by contractors. Photo Aug. 28, 2015

Closed to the public for more than two years, including more than a year after the $1.36 million taxpayer-funded solar-irrigated “erosion control” project was completed, the ugly, massively enlarged outfall draining Post Oak Road is still officially a Texas Parks and Wildlife Paddling Trail boat launch. Previously it was also a forested area with a nature trail.

But officials with the Uptown Tax Increment Reinvestment Zone (TIRZ) 16 now seem genuinely eager to do “what we can to get it open to the public,” said John Breeding, administrator, at the Uptown board meeting in a Galleria high-rise last Wednesday, Aug. 26.

The board voted without discussion to award a contract for $219,272.10 to Jerdon Enterprise, LP, which was the sole bidder for the long-delayed project. With “add-ons” the cost could go to $335,615.10. That seems like a lot of public money for taking down some chain-link fencing, putting up some standard railing, laying down some loose gravel, etc. But apparently no one else wanted to do it.

Work on the Outfall Phase II is now scheduled to begin this month and be completed by December 15, 2015.

And if you’re confused about why a TIRZ and not the parks department or the city council would be making these decisions, well, it is confusing. But the TIRZ has control of the money.

Read the rest of this post.