Another Failed Erosion Control Project on Buffalo Bayou

July 15, 2014

Kayaked down Buffalo Bayou past Memorial Park the other day with geophysicist Richard Hyde, a longtime supporter of Buffalo Bayou, an early member of the Bayou Preservation Association, and an opponent of the BPA’s very bad plan to destroy the natural beauty of Buffalo Bayou in order to … well, no one can quite figure out the purpose of this bizarre and heart-breaking project that would raze over a mile of perfectly fine riparian forest along both banks in and around our great Memorial Park. The proposal, created and promoted by the BPA and officially a project of the Harris County Flood Control District, would also dig up and fill in the bayou, its banks and high bluffs, dam up or bulldoze tributaries, causing enormous loss of land and forest to the River Oaks Country Club, which is paying $2 million for the privilege. It is a mystery why anyone thinks this is a good idea; a mystery how a project with no public benefit and so much public harm ever got funded ($4 million from county and city taxpayers); and a mystery why the BPA, an organization founded to “preserve the natural beauty” of the bayou, would be so hell-bent on eradicating it.

The water was very low — known as base flow, the bayou’s natural flow during fair weather, which is very slow and shallow. Except it wasn’t really base flow because a thunderstorm had just passed over, so even as we were slip-sliding in under the Woodway bridge the water was rising and the current picking up from runoff.

Our first shocking encounter was the new Woodway drainage outfall, recently constructed at a cost of $1,147,934 to Houston taxpayers (i.e. taxes that went to the Galleria area TIRZ 16 rather than into the city treasury). Laughably, this project, no longer under construction but still closed to the public, is described as an “erosion control” project in the TIRZ 16-Uptown 2013-2017 Capital Improvement Plan. “This drainage outflow project is to mitigate erosion in banks of Buffalo Bayou at Woodway,” says the budget description.

Please note the horrific erosion from the dissolving banks of this new massive outfall, the sand and mud clogging the channel, the concrete sidewalk and steps. There were trees here once, and a nature trail. Update 8.4.2014: In 1848, the rock-bottomed ford here was known as “Dutchman’s Crossing.”

Photo taken July 15, 2014, of mud and sand eroding from sides of new drainage outfall at Woodway on Buffalo Bayou.

Photo taken July 15, 2014, of mud and sand eroding from sides of new drainage outfall at Woodway on Buffalo Bayou.

The budget shows no funds allocated for operating and maintenance.

The big, new drainage pipe was also supposed to be set at an angle that allowed the often powerful flow of water to be released in the direction of the flow of the bayou, instead of shooting directly at the opposite bank. But apparently someone forgot to tell that to AECOM, the engineers who designed the project (as well as the tragically unsuccessful “erosion control” project at the Houston Country Club, which razed much of the riparian forest buffer on the banks of Buffalo Bayou along its golf course). AECOM designed the Woodway outfall so that the water blasts directly at the opposite bank, which is already being eaten away by the force.

The big new outfall shoots stormwater directly across the bayou at the opposite bank. Oops. Maybe they want the bayou to erode?

The big new outfall shoots storm water directly at the opposite bank and sediment into the bayou. Oops. Maybe “erosion control” means “increasing erosion”?

Mr. Hyde just shook his head.

This “erosion control” project is in City Council Member Oliver Pennington’s district and Mr. Pennington is running for mayor, as he tells everyone he meets, so be sure to let him know what you think about Mr. Pennington’s “erosion control.” He’s holding a public meeting on Wednesday, July 30, 2014, from 6:00 to 7:30 pm at St. Anne’s Catholic Church, St. Basil’s Hall, 2140 Westheimer (at the corner of Shepherd). The meeting is to discuss “storm drainage improvements” on Shepherd from Westheimer to Buffalo Bayou. The project is scheduled to begin in a few weeks and will last over a year, so it’s very kind of Mr. Pennington to offer a public meeting about it.

Mr. Pennington supports the “erosion control” project that requires razing the wild banks and destroying our natural bayou in and around Memorial Park. So let him know what you think about that too. Might be time to bring out the pitchforks pickets and banners.

To be continued.

 

 

 

 